Let us save clean environment for future generations

About us

Heat Economy to Raise the Price of Heating

2009-11-30

 

Production Price Lowest in the Country
 
Kaunas Heat and Power Plant (KHPP) is the major and cheapest heat generator in the city, this power plant produces more than 95 % of heat to Kaunas; its price reaches 14.7 cents per kilowatt-hour. This happens to be one of the lowest prices in Lithuania. Prices of other heat generators in Kaunas are higher approximately by 10 cents.
 
Nevertheless, energy experts have noticed long ago that paradoxical situation happened in Kaunas: despite one of the lowest heat production prices in Lithuania, heat transfer and sales prices appear to be one of the highest. Given that, final prices to the consumers are also high.
 
Energy specialists state that without the renewal of the overall heat sector there is no need to expect lower heat prices in Kaunas.
 
“It is necessary to modernise heat networks in Kaunas city because a lot of heat is being lost, which needs to be covered by consumers. After all, the heating line in the city was laid during the Soviet times still. Pipes are too large in diameter because then it was predicted that the number of heat consumers would rise”, stated professor Eugenijus Ušpuras, the Director of the Lithuanian Energy Institute.
 
According to him, the current situation is opposite – heat consumers are likely to decrease in Kaunas city because part of the households are disconnecting from district heating, whereas large-sized business companies have their own pipelines. Thus, it should be well thought over how the current situation of heat economy might be improved. One of the solutions is to replace the existing pipes by those of smaller diameter and better insulation.
 
Hopes in the New Power Plant
 
Hopes to renew the heat economy in Kaunas are, first of all, related to the combined heat and power plant, which is already drawn in the designs. At this moment such power plants are distinguished for the most efficient energy generation technology.
 
“The future power plant, the capacity of which may reach 350 megawatts, will use natural gas, but in the future, once special equipment is installed, it will be possible to burn biogas and use the steam, produced by domestic waste incineration company”, said Arvidas Ladyga, the Technical Director of Kauno elektrinė, which is implementing the project for the power plant construction.
 
Technologies of combined gas turbines stand out for low level of pollution and high efficiency in energy production. Let it be assumed that efficiency of energy generation at Göteborg power station (Sweden) reaches 92.5 % (electricity – 43.5 %, heat – 49 %).
 
Boiler Houses Have Already Worked Out
 
According to Mr Ladyga, current facilities at KHPP are already out-of-date as there have been no essential reconstruction works at the power plant during the last 20 years. Moreover, other boiler houses in Kaunas, which belong to Kauno elektrinė, are also dated.
 
“Heat production boilers in Kaunas are old and their performance is not productive. Average working life of boiler at boiler houses at Petrašiūnai power plant, Šilkas and Inkaras districts exceeds 40 years. Weighted average working life of boilers at Pergalė district boiler house, as well as boilers maintained by KHPP, is approaching the critical limit of performance, i.e. 30 years. Thus, on the basis of such figures only, we may notice that investment striving for the increase in the reliability of energy production is indispensible”, asserted representative of Kauno elektrinė Mr Ladyga.
 
Millions Will Not Save the Company
 
Networks, controlled by Kauno energija, were planned to be renewed a couple of years ago when financial injection (116 million litas) for the sold thermal power plant was received from the Russian concern GAZPROMin 2003. However, the money was used to cover up debts only.
 
The former Kaunas city government failed to turn Kauno energijainto a successful company. On the contrary, in 2007 losses suffered by Kauno energija made up 8.6 million litas. Part of company’s assets was sold out also: steam pipe – for 2.03 million, gas pipeline – for 3.46 million litas. Even the price of heat production, which had been augmented by KHPP for five years, did not save the situation.
 
“Receiving heat at the lowest prices, the government failed to do anything to modernise heat distribution networks during all these years. This is an example of mismanagement; pipelines are worn out to a critical limit. It requires around 50 million litas per year to renew the lines”, said an energy expert, who preferred staying anonymous.
 
Rimantas Bakas, the Director General of Kauno energija, approved that the status of the urban heat lines is just sufficient.
 
“For the renewal of networks we allot up to 10 million litas per year. So that the average working life of networks stops increasing at least, it is necessary to allot twice as much, i.e. around 20 million litas on an annual basis”, explained the Manager of Kauno energija Mr Bakas.
 
Planning to Burn Biomass
 
Kaunas heat economy could be modernised in two stages: 2010-2015 and 2016-2022. During the first stage a new combined heat and power plant would be constructed and the heat capacity would reach up to 350 megawatts. Optimal capacity of a new power plant must be determined by bringing in the experience of experts from Finland or Switzerland.
 
In order to increase the reliability of heat distribution, reserve heat sources of integrated network and water heating boilers with the capacity not less than 200 megawatts would be renewed. This would allow reducing maintenance costs. Moreover, in boiler houses, where fuel is relatively expensive, wood waste may be started to be burnt.
 
Once the works of the first stage are accomplished, heat price to Kaunas residents will be at the lowest level, whereas heat economy would be one of the most modern in the European Union. At the second stage the issues of the construction of domestic waste and biomass incinerators will be considered. Waste and biomass facilities may be equipped also in the place of old facilities of Kaunas power plant. Such a model would be the cheapest to the city.
 
Constructors to Have Work Too
 
The new combined heat and power plant should come into operation in 2013. Investment into it will be likely to reach around one billion litas. An international contract tender will be announced for project implementation. It is clear, however, that the major suppliers will be from the West, namely the energy concerns “Siemens” (Germany), “General Electric” (USA) or “Alstom” (France).
 
At the moment preliminary works for the construction of the power plant are about to be completed. Even during these hard times Western finance institutions agree to finance the project. Shortly, procedure for drawing up a detailed plan with Kaunas Municipality will be given a start. Additional income will be obtained by the state and the city municipality from commercial activity of Kaunas power plant. It has been estimated that within 30 years taxes to the state and municipality will make up 280 million litas (35 million to the municipality). In the course of construction works taxes to the state will reach around 22 million litas and about 3 million to Kaunas city.

© Kauno diena

Other articles